Implementation plan and fundraiser
Survey results
- Feedback obtained from 160 households to December’s door to door survey (~30% of the village)
- Additional discussions with the children at the village school and at cubs
- 98% (157 households) were in support of the project with 80% preference to use the tennis court site for one tennis court and one multi-use games area (MUGA)
Timetable
- Resurfacing work planned to be completed in the Spring
- Tennis court and multi use court lining in time for the Summer
- New tennis posts and net installed for the Summer
- Multi use goals also in place by the Summer (subject to securing final funding)
SAVE THE DATE!!
Friday 19th April, 7.30pm
Quiz night, Hunsdon Village Hall
Volunteers and Contact Information:
Volunteers always welcome, to help with upkeep of the area & future fundraising